Wrong Absence Duration Calculation When Using Work Schedule

(Doc ID 1607139.1)

Last updated on AUGUST 24, 2017

Applies to:

Oracle Human Resources - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On 12.1.3 version, Absence recording, maintenance

ACTUAL BEHAVIOR
---------------
Absence duration calculation is returns zero for future dated assignment.

Ex: if the assignment record like below.

09-OCT-2013 to open ended.
01-JAN-2008 to 08-OCT-2013

and if you try to apply leave before 09-OCT-2013 the duration is coming as ZERO.

and If you apply leave 09-OCT 2013 onwards the duration shows correctly.

EXPECTED BEHAVIOR
-----------------------
It should display correct duration either the of the case.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to HRMS Manager -> People -> Enter and Maintain -> Other-> Absence
2. Enter the Leave for example from 06-OCT-2013 (08:30) to 06-OCT-2013 (17:00)
3. Duration displayed as ZERO instead of 7.5 hours

NOTE: You are NOT using the BG_ABSENCE_DURATION but use WORK SCHEDULE pattern.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms