On : 12.1.3 version, Demand Processor Related Issue

ACTUAL BEHAVIOR
---------------
Per customer:
The Replace functionality in RLM is not working as expected.When we process the new schedules with replace
functionality it is not updating the earlier schedule.In the sales order board we are still able to see the
reference of the old schedule number instead of the new one in the industry attributes.  RLM General/Demand
Stream Process Issue for process number 866, 830 or 862

This is happening in PROD instance and is critical.

EXPECTED BEHAVIOR
-----------------------
Expect the Replace Functionality to do just that, replace earlier schedules such that there is no reference to
the old schedule number

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Release Management responsibility
2. Run DSP with Replace functionality
3. Results are not what are expected

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, in the sales order board users are still able to see the reference of the old schedule
number instead of the new one in the industry attributes..

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms