Cost Budget Will Not Generate From Staffing Plan (Doc ID 1618950.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Management - Version 12.1.3 to 12.2.4 [Release 12.1 to 12.2]
Information in this document applies to any platform.
PAFPCALB.pls
BUDGET
STAFFING PLAN

Symptoms

Trying to generate a cost only budget from a staffing plan. Hours are populated, planning rate is populated but amount won't calculate.
Seems as if something related to the spread is resulting in amount in each month and then the full amount being reversed in the final month based on the diagnostic.

Cause