R12: PRC: Generate Asset Lines Process Does Not Pick Up Eligible Expenditure Items (Doc ID 1621415.1)

Last updated on JUNE 29, 2017

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.
PRC: Generate Asset Lines for a Single Project process

Symptoms

On : 12.1.3 version, Asset Capitalization

When attempting to generate asset lines via PAXCPGAL_SINGLE module: PRC: Generate Asset Lines for a Single Project,
eligible expenditure item is not being picked up. The output file shows rejection:

REJECTION
-----------------------
*** No Data Found ***


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run PRC: Generate Asset Lines for a Single Project,
2. Review the output file and see the rejection: *** No Data Found ***

Cause

Sign In with your My Oracle Support account