R12 PAXEXCPD EXC: Transaction Exception Detail Gives "Oracle Projects has not Processed New Line. Please verify if the accounting for the invoices is complete and then rerun the PRC: Interface Supplier Costs concurrent program." (Doc ID 1622640.1)

Last updated on FEBRUARY 06, 2017

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Unable to close the Project's period as the following exception is being received:

Period : DEC-13

Exception Reason : Oracle projects has not processed the new line

Corrective Action : Please verify if the accounting for the invoices is complete and then rerun the PRC: Interface Supplier Costs concurrent program

Cause

Sign In with your My Oracle Support account