Service Request Form: Task Planned Effort Calculated As Zero When Entering/Changing the Scheduled End Date for a Task
(Doc ID 1628848.1)
Last updated on FEBRUARY 06, 2022
Applies to:
Oracle Teleservice - Version 12.1.3 to 12.1.3 [Release 12.1]Information in this document applies to any platform.
Symptoms
On : 12.1.3 version, Service Request Form -> Task Tab
ACTUAL BEHAVIOR
---------------
When entering the scheduled end time, the Planned Effort value is updated to 0 (zero).
EXPECTED BEHAVIOR
-----------------------
Expect the correct Planned Effort to be calculated and displayed.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. In the Task tab, create a task
2. Enter the Scheduled Start and End times,
3. Planned Effort field is automatically updated to zero.