'Create Asset Headers In Oracle Projects - Normal Items' Is Not Creating Asset Headers For Capital Projects Debug shows error 'You do not have update privileges on this project.'

(Doc ID 1639393.1)

Last updated on MAY 19, 2017

Applies to:

Oracle Asset Tracking - Version 12.1.3 to 12.2.3 [Release 12.1 to 12.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When attempting to run the 'Create Asset Headers in Oracle Projects - Normal Items', nothing is processed.

EXPECTED BEHAVIOR
-----------------------
Expect the program to create Asset Headers for records that are prepared.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Navigation: Inventory >> Transactions >> Miscellaneous Transaction

Perform "Issue to Project" transaction

2. Setup >> Transactions >> Interface Managers

Validate that the Cost Manager is active and has costed the transaction receipt

3. Navigation: Asset Tracking Super User >> Inventory >> Accounting Close Cycle >> Project Cost Transfers

Launch the Cost Collection Manager

Parameter - 'Number of Days to Leave Costs Uncollected' = 0 to cost the issue transaction as it is related to Projects.

Validate that the transaction issue has been costed

4. Request >> Run

Select 'PRC: Transaction Import'
 
Parameter - 'Transaction Source' = 'CSE_INV_ISSUE' to create expenditure items in the project

Validate that the expenditure is created and DFF Segments 7 and 8 are populated

5. Assets >> Deployment

Perform an 'Install' transaction on the Serial

Validate that the Instance has the following:

Accounting Classification - Inventory
Operational Status Code - Installed

6. Assets >> Deployment

Perform an 'In Service' transaction on the Serial

Validate that the Instance has the following:

Accounting Classification - Inventory
Operational Status Code - In Service

7. Navigation: Cost Management - SLA >> SLA >> Create Accounting

Run the 'Create Accounting - Cost Management' process

Validate that the accounting is correct

8. Request >> Run

Select 'Interface In-Service Transactions to Oracle Projects - Normal Items' for the Project and Task

Validate that there is an entry in the PA_TRANSACTION_INTERFACE_ALL table.

9. Request >> Run

Select 'PRC: Transaction Import'

Parameter 'Transaction Source' = 'CSE_INV_ISSUE'

Validate that expenditures were created for both transactions

10. Request >> Run

Select 'Create Asset Headers in Oracle Projects - Normal Items'

11. The program completes but does not create asset headers in the project.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms