The List Of Values (LOV) For Projects Is Not Limited To The Projects Tied To The Purchase Order (PO) Item In Mobile (MSCA) (Doc ID 1641683.1)

Last updated on JULY 17, 2017

Applies to:

Oracle Inventory Management - Version 11.5.10.CU2 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
The list of values (LOV) for Projects is not limited to the projects tied to the purchase order (PO) Item in the Mobile Supply Chain Application (MSCA).
 
EXPECTED BEHAVIOR
Expect that the LOV for Projects will only include those projects tied to the P.O.

STEPS
1. Receiving a single line against multiple line PO
2. Select the PO
3. Enter the item number
4. Use the LOV for project.
* The LOV is NOT limited to the Projects tied to that PO/Item. The LOV instead brings back all projects on that PO and allows you to select and continue with the wrong project in the locator. It only errors out when you go to save the transaction, but does not tell you what went wrong.

BUSINESS IMPACT
This is one of our biggest issues. On multiple line PO's and multiple projects the PO is not pulling in the project #'s. When using the LOV it should only show you what project #'s are available for the line # but it shows all project #'s.

Cause

Sign In with your My Oracle Support account