Resource Utilization Creating Incorrect Resource Requirement On Source & Planning Application (Doc ID 1662162.1)

Last updated on OCTOBER 28, 2016

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When setting a Utilization on a resource ASCP inflates the Adjusted Resource Hours in line with the utilization and this is expected but the batch is also created with the same inflated value and this is not expected

EXPECTED BEHAVIOR

It is expected the batch will be created without the inflated resource requirements.

STEPS

The issue can be reproduced at will with the following steps:
1. Have a Plant Resource with a utilization
2. Collect and plan, see that the adjusted resource hours reflect the utilization
3. Release the planned order to create the batch and see that the APS details have been passed from the log file.
4. See that the batch has also been created with the inflated resource value

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms