Mass Update On Purchase Requisitions Does Not Update Preparer As Requested (Doc ID 1663016.1)

Last updated on MAY 06, 2014

Applies to:

Oracle Purchasing - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.1 version, Reports - PO and RCV

Mass Update on Purchase Requisitions to update preparer, but the preparer does not get updated.

STEPS TO REPRODUCE
-----------------------
1. Run the concurrent program: Mass Update on Purchase Requisitions
Old person =Radhe, W (2266)
New Person = Jeu, C.J. de (52386)
For Requisition 10100003615

2. The request is completed without error, however, sysdate of the po_requisition_headers_all table is updated but the preparer_id is not.

Cause