Symptoms

On : 12.1.3 version, Trx Changes & Cancellations

ACTUAL BEHAVIOR
---------------
 When using the public process Order API OE_ORDER_PUB.PROCESS_ORDER for line spliting the order lines this API deleting the Line reservation.

EXPECTED BEHAVIOR
-----------------------
Expected is that the reservation should remain on the parent line when split is performed using process order API

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

Issue is with the reservation is getting removed by the oe_order_pub.process_order API.

1. Create a B2B Order and create a Line with 18000 pcs as ordered quantity.

2. Create a PO against it and also with a 18000pcs PO line.

3. Partial Receive the PO Line with 3000pcs and then 3000pcs is getting reserved on the Order Line successfully which is working as expected till now.

4. Call the oe_order_pub.process_order API to split this order into 2 lines with 12000(Line 1.1) and 3000(line 1.2).

5. The reservation is lost on the both the line 1.1 and 1.2. The correct functionality should be the reservation will be moved to Line 1.2.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms