Unable To Baseline An Approved Revenue Budget

(Doc ID 1673240.1)

Last updated on FEBRUARY 09, 2018

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.


When attempting to baseline an approved revenue budget, user receives the error:

Project Funding is not equal to the budget total. To baseline a draft budget, the budget total must be as same as funding total.

Users reviewed the funding under the agreement and the amounts match.