Unable To Baseline An Approved Revenue Budget (Doc ID 1673240.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.
***Checked for relevance on 22-OCT-2015***

Goal

When attempting to baseline an approved revenue budget, user receives the error "Project Funding is not equal to the budget total. To baseline a draft budget, the budgtet total must be as same as funding total". Users reviewed the funding under the agreement and the amounts match.
 

Solution