Cost Relieved Is Higher Than The Cost Incurred (Doc ID 1674557.1)

Last updated on JUNE 20, 2017

Applies to:

Oracle Cost Management - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

On : 11.5.10.2 version, WIP Costing

ACTUAL BEHAVIOR
---------------

For some jobs, the cost relieved is higher than the cost incurred


We will upload details

EXPECTED BEHAVIOR
-----------------------
No variances between incurred x relieved costs

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

a) We create a WIP job,
b) We charge components, labor and overhead to the job,
c) We complete the job where the sum of all cost charge is relieved to the unit cost for the assembly completed.

The problem occurs for some jobs, the cost relieved is higher than the cost incurred.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms