R12 PAXURVPS Canceled Requisition Still Appears In Project Status Inquiry form (Doc ID 1676524.1)

Last updated on JULY 23, 2016

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.
*** Checked for relevance 08-Dec-2014 ***

Symptoms

On 12.1.3, Expenditure Processing:

A canceled requisition still appears in the PAXURVPS Project Status Inquiry form.  The users added to commitment amount after running PRC: Update Project Summary Amounts program due to CLM.  

New records are  created for every requisition.

Cause