Goal

In the Visit Work Package (VWP) Tasks screen, why are the NR's associated stages NOT showing up ie. Stage Name has NULL values ?

Steps
1. Update Work Order (WO)
2. Add Non-Routine (NR)
3. Attach 1 MR (with mapped Stage Types)
4. In the Visit Work Package screen .. noted the NR's tasks/wo were NOT displaying the mapped Stages.

Solution