Unable To Change Cost Group For A Project Where Transactions Already Exist

(Doc ID 1683935.1)

Last updated on JUNE 08, 2017

Applies to:

Oracle Project Manufacturing - Version 12.1.2 and later
Oracle Project Costing - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Goal

Changing the way track costs within project manufacturing based environment.

Currently have an active project assigned to a cost group and have been using this project for quite some time. There are many transactions for the project.

When attempting to change the project's cost group from the Project Parameters form. Get the error message APP-PJM-58504.

Is there a procedure or method that would allow us to change the cost group for a project ?
 

Solution