Work Orderless Completion (WOC) Transactions Doesn't Close the Flow Schedule (Doc ID 1900953.1)

Last updated on OCTOBER 15, 2015

Applies to:

Oracle Flow Manufacturing - Version 12.1.2 to 12.2.4 [Release 12.1 to 12.2]
Oracle Bills of Material - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

After performing a work order less completion, the flow schedule is not automatically closed.

Expect that the flow schedule is closed.

Steps to reproduce the issue:

1. perform work order less completion and observe the flow schedule is still open

Cause