Symptoms

On : 12.1 Rup 5 version and above of the Application, In the Leave Of Absence Form.

ACTUAL BEHAVIOR
-----------------------------

Leave duration is always calculated as "Zero", when the Work Schedule is mapped to employee via HR Location.

EXPECTED BEHAVIOR
-----------------------------

Expect that, Leave duration should be calculated correctly based on the Work Schedule mapped to the employee via HR Location.

STEPS
-----------------------

The issue can be reproduced at will with the following steps:

1. Login using "HRMS Superuser" responsibility.

2. Navigate to Work Structures --> Work Schedules --> Maintain Schedules --> Schedules.

3. Create a New Schedule and add resource to the schedule based on the Type "HR Location".

4. Also set the Profile "HR: Schedule Based Absence Calculation" to "Yes" at Responsibility Level.

5. Now try to apply for leave, it will be seen that the Leave Duration is always calculated as "Zero". Behavior is same in Professional User Interface (PUI) as well as Self Service.

6. Also in the "Assign Schedule" form schedule mapped to the employee via his HR Location is not shown.

BUSINESS IMPACT
-----------------------

The issue has the following business impact:

Due to this issue, When applying for leave, duration is not getting calculated automatically.

Users are forced to enter the total days manually which is not recommended.

Work Around:
-------------------

Have to manually override the duration value of zero each time the leave has to be submitted.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms