Project Agreement Amount And Funding Amount Not Equal, Funding Reevaluation Occuring for Same SOB
Last updated on MARCH 08, 2017
Applies to:
Oracle Project Billing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
PAXINVPF and PAXINEAG Funding discrepancy
The Agreement Amount was: 12,770,000.00
Funding Amount Total: 12,770,000.00
When we check on Funding Inquiry screen : 7,662,000.00
Difference: 5,108,000.00 --- the amount of the revaluation
Funding revaluation process, reevaluates even when funding currency code and project functional currency code are same
Cause