R12: Attempt To Run "PRC: Submit Interface Streamline Processes" With DXL Option, The "PRC: Distribute Labor Costs" Process Fails With "Signal 11" Error (Doc ID 1909346.1)

Last updated on MARCH 06, 2023

Applies to:

Oracle Project Costing - Version 12.2.3 and later
Information in this document applies to any platform.
PALDLC: PRC: Distribute Labor Costs

Symptoms

When running the 'PRC: Submit Interface Streamline Processes' with streamline option 'DXL: Distribute and Interface Labor Costs to GL',

the 'PRC: Distribute Labor Costs' process fails with 'Signal 11' in the request log file:


PALDLC: PRC: Distribute Labor Costs
+---------------------------------------------------------------------------+

Current system time is 26-JAN-2016 16:26:17

+---------------------------------------------------------------------------+

 Parameter ARG_EXP_GROUP_NAME = []
 Parameter ARG_PROJECT = []
 Parameter ARG_PERSON = []
 Parameter ARG_END_DATE = []
 Parameter ARG_INCURRED_ORG = []
 Parameter ARG_R_INTERVAL = []
 Parameter ARG_R_TIME = []
 Parameter ARG_R_STOP_DATE = []
 Parameter ARG_R_ADJ_DATES_FLAG = [N]
 Parameter ARG_DEBUG_FLAG = [(null)]
 Parameter ARG_FROM_PROJECT = []
 Parameter ARG_TO_PROJECT = []
 Parameter ARG_ACCRUAL_FLAG = []
Reading the request id parameter
/u02/oracle/DEV2/fs1/EBSapps/appl/pa/12.0.0/bin/PALDLC
Program was terminated by signal 11

If users submit the "PRC: Distribute Labor Costs" outside the Streamline process, it completes successfully

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.