Incorrect Remaining Commitment Cost for a Partially billed PO in PSI? (Doc ID 1911668.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

 Why for a particular PO that has been partially billed, the remaining commitment in PSI is not equal to : purchase order amount - billed amount, but shows a higher amount?

Solution