There is an unexpected gap in the ASCP scheduling of resource requirements/operations

(Doc ID 1913779.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.2.1 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.1 version

ACTUAL BEHAVIOR
---------------
In the resource requirements for an ASCP Planned Order for an OPM Make item there is a substantial gap between the end date of the penultimate operation relative to the start date of the final operation. The final operation has a very long lead time compared to the other operations in the route.

EXPECTED BEHAVIOR
-----------------------
There to be no gap between the end of the penultimate resource requirement and the final resource requirement

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Set up as above
2. Run the ASCP Standard Collection, complete refresh
3. Run the Enforce Demand Due Date Constrained (with Detailed Scheduling) ASCP Plan

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot rely on the results of ASCP

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms