Why Don't The End Dated Expenditure Types Appear In List Of Values In The PAXPREPR Projects -> Transaction Controls Option? (Doc ID 1914507.1)

Last updated on AUGUST 01, 2016

Applies to:

Oracle Project Billing - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

In the PAXPREPR Projects - Transaction Controls form, the list of values does not display Expenditure Types that have been End-dated.

However, the end-dated Expenditure Types do appear in the Non-Labor Bill Rate and Discount Overrides option in the same project form.

Why isn't the End-Dated Expenditure Type allowed in the Transaction Controls?
 

Solution