19462516: PRC: Interface Supplier Costs Running 2 Hours After Family Patch R12.PJ_PF.B.delta.6 (Doc ID 1920531.1)

Last updated on JUNE 29, 2017

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Purchase to Pay Flow

ACTUAL BEHAVIOR
---------------
PRC: Interface Supplier Costs program is running for nearly 2 hours. This is since we have applied patch 17839156.B Oracle Projects Release Update Pack 6 for 12.1 (R12.PJ_PF.B.delta.6)

EXPECTED BEHAVIOR
-----------------------
PRC: Interface Supplier Costs program should run in a reasonable amount of time.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run the PRC: Interface Supplier Costs program


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Family Packs should go live in September 2014. 300 users are affected

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms