Using Purchasing, when entering the buyer work center and choosing the Schedules tab - the line quantity is defaulting to the shipment quantity
even though there was a previously cancelled shipment that is fully obligating the line.

Steps to reproduce

1. Login to the E-Business Suite and choose the Purchasing Module.
2. Create a purchase order - quantity of 50
3. Receive a quantity of 45
4. Using the core purchasing form - cancel the remaining 5
  - The line is still available - increase this to 50 - Save
5. Move to the buyer work center and query the purchase order for update
 - Choose the line - note it has 50
 - Choose the schedule tab - note its putting in 50 for the quantity - but it should be 5

The core application purchase order form calculates the quantity properly, the new shipment 2 shows a quantity of 5 - rather than 50.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms