ASCP/OPM Unconstrained Plan Not Able To Convert The Planned Orders With Auto Release. (Doc ID 1925781.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, APS Feedback

When attempting to release an ASCP planned order for an OPM make item from an Unconstrained plan
the following error occurs.

ERROR
-----------------------


GMPRELAP module: Auto Release of Planning suggestions for APS

===== Input Parameters =====
p_process_id = 33056960
p_organization_id =
p_fitem_no =
p_titem_no =
p_fdate =
p_tdate =
Implementing Batches
New btach Processing for Group ID = 33056960 Header ID = 69306
Before validate Effectivity
p_organization_id 9804
p_inventory_item_id 37182613
p_effectivity_id 122
p_plan_quantity 15000
Batch type 0
p_start_date 27-SEP-14
p_end_date 29-SEP-14
 No effectivity id
After validate Effectivity
l_recipe_id 28
l_return 1
Calendar Code CHEM_JH
Start Date 09/27/2014 00:00:00
End Date 09/29/2014 00:00:00
CHEM_JH
29/09/2014 00:00:00
Nearest End Date = 09/27/2014 23:00:00
Completed GET_CONTIGUOUS_PERIODS09/05/2014 10:52:46
Completed GET_CONTIGUOUS_PERIODS09/05/2014 10:52:46
 Error - Status is E or U User-Defined Exception
:1:The planned start date or planned completion date, or both dates are outside the date range specified by the validity rule.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Release a planned order from an Unconstrained Plan for an OPM make item

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot create batches in this way

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms