Packing LPNs With Different Deliv. Into a Master LPN created a Trip Stop Sequence =0 (Doc ID 1931757.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Shipping Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

PROBLEM STATEMENT
=================

On: 12.1.3

When attempting to  pack LPNs with multiple deliveries into one master LPN using staging move,
sequence number for one of the trip stop is showing as "0"

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Operation Plan: Outbound Consolidation across deliveries.
2. Trying to Drop LPN 273 into LPN 266 during staging Move
Both LPN's belong to two different deliveries but have same Intermediate Ship To
3. Confirm the Subinventory and locator and click on Done button.

4. The trip is created with sequence = 0


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot go-live.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms