Inventory Move Order Allocation Does Not Allocate Stock From Correct Project And Task (Doc ID 1934790.1)

Last updated on DECEMBER 02, 2016

Applies to:

Oracle Warehouse Management - Version 12.1.3 and later
Oracle Inventory Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Material Move Orders

In PJM enabled organisation for which 'Allow Cross Project' parameter is not checked , move order allocation process is not honoring project and task of the move order (Project and task entered when move order created).

System is allocating stock from other project and/or task (Allocation created with a locator related to other projects / tasks).

Expect system to allocate the stock from the same project and task that was specified for the move order.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms