How To Set Resource Specific Workdays Calender? (Doc ID 1936899.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

On : 12.1.3 version, Install/Configuration

How to set resource wise Workdays calender?

I would like to know how to set resource wise Working hours. Currently I set working days calendar as 4:00 AM to 11:59:59 PM but we have some resources which runs 24 hours. Due to this when I ran ASCP plan it gives me starts and completion time base on 4:00 AM to 11:59 PM calendar.
 

Solution