Symptoms

On : 12.1.3 version, Intelligence Setup

ACTUAL BEHAVIOR
---------------
After <patch 16961606> has been applied, the Budgets and Forecasts amounts in the DBI for projects multiplies every time the concurrent program "PRC: Update Project Intelligence Data" is being ran, instead of just being refreshed.

Note : Running "PRC: Refresh Project Intelligence Data"  clears the issue

EXPECTED BEHAVIOR
-----------------------
The Budgets and Forecasts amounts should be accurate and not double or tripled.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Submit the concurrent program "PRC: Update Project Intelligence Data"

BUSINESS IMPACT
-----------------------
The Budgets and Forecasts amounts are wrong in the project intelligence

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms