Symptoms

On : 12.2.4 version, Shipment Issues

When attempting to perform correction on Work Confirmation, the following error occurs.

ERROR
-----------------------
Line 1, Pay Item 1: Total Requested/Delivered Quantity to date (8.0) cannot exceed Ordered (10.0) + Over-Receipt Tolerance (0.0)


STEPS
-----------------------
1. Purchasing -> Create a Complex PO with the Line Type “Rate”.
2. In the Pay Items, normally the Over-Receipt Tolerance is displayed as zero by default.
3. Create a Work Confirmation for 100%
4. Now, try to correct the Work Confirmation to 80%
5. Error occurs


Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms