Error APP-GMA-80310 When Entering Resource Transactions on Completed Batches (Doc ID 1948114.1)

Last updated on NOVEMBER 03, 2016

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Batches

An OPM batch is released and completed without explicitly releasing steps. The system automatically completes steps using work order completion date as step start and step completion date.

Then a resource transaction is entered.

The system uses work order completion date as resource start date and calculates resource completion date based on usage

On an older instance we have version 12.0.110.12010000.25 of GMESTPED and scenario above works fine without error

On that older instance system uses work order completion date as resource completion date.

ERROR
-----------------------

By doing so it can get into future and gives error APP-GMA-80310, The Date Entered can not be in the Future

This is on form version 12.0.110.12010000.31 of GMESTPED.



STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. An OPM batch is released and completed without explicitly releasing steps.
2. A resource transaction is then entered.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot enter resource transactions to batches whose completion date along with the resource's lead time would cause the resource completion date to be in the future.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms