Batch Reschedules From PS -> OPM Failing For Some Steps (Doc ID 1949743.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.8 and later
Oracle Process Manufacturing Process Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.8 version, Release Planned Orders To EBS

When attempting to publish reschedule actions against existing OPM batches
the following error occurs.

ERROR
-----------------------

GMPRELAP module: Auto Release of Planning suggestions for APS

Inside GME Way
updaing gme_batch_step_resources
gme_batch_step_resources GME way
Failed: Resource Transaction Step Resource failed: GME way
::-6::Update to step resources failed. Details of the batch will NOT be synchronized.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Publish reschedule actions within PS for existing OPM batches

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot understand the time differentials between the result in PS and the result in OPM batches post reschedule

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms