Funds check result 'Budgetary control failed due to incomplete transfer of data' after upgrade. (Doc ID 1950026.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On :  12.1.3 version, Funds Check

Funds check returns 'Budgetary control failed due to incomplete transfer of data' after upgrade.

After Upgrade to R 12.1.3 the result of the funds check in PA for all projects is 'Budgetary control failed due to incomplete transfer of data'.  This worked without problems for the same projects in R11.

ERROR
-----------------------

Budgetary control failed due to incomplete transfer of data

Cause

Sign In with your My Oracle Support account