ACTUAL BEHAVIOR

When trying to create a non-standard discrete job using an alternate routing and selecting the alternate in the Routing Tab, the Completion Subinventory is not automatically populated based on the routing for the alternate.
However, when creating a standard job and using the alternate, then the Completion Subinventory is defaulted correctly.


EXPECTED BEHAVIOR

When Routing and alternate routing have defined different completion
subinventory in Routing details, for non-standard job, changing alternate field should reflect completion subinventory as per Routing setup.


STEPS

The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process
2. Navigation: Discrete -> Discrete Jobs
3. Create Job = 10 with Status = Unreleased
4. Under Routings tab as an example:
    Reference = ARRIS502G
    Subinventory = C Retail R
  Locator = 1.FLOOR.CRET
5. The Completion Subinventory (C Retail R) should have been the Completion Subinventory populated per the Alternate Routing, which is C Retail N.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms