PA Budget Line Record Gets Deleted If User Blanks The Period Amount (Doc ID 1957330.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Management - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.3 version, Budgeting & Forecasting

PA Budget Line record gets deleted if user blanks the period amount

PA Budget Line record gets deleted if user blanks the period amount that was previously entered. We are using logic to determine the delta amount between the previous baselined version and the current amount for the budget line. If the user blanks out the period amount then we are not able to get the delta. This however works if the user enters 0 in the field rather than blank