Goal
Which calendar will be considered in OPM production batch? resource calendar or inventory organization calendar?
1. Setting up the calendar in Inventory:
Inventory > Set up > Organizations > Calendars > Create calendar in Workday calendar > Tools > Build
2. Attach calendar to resource in process engineer:
Process engineer > Set up > Plant resources > Resource information > Search resource information > Add required calendar into calendar field in both material and labour plant resources
3. To generate resource availability in OPM Supply chain superuser:
OPM Supply chain superuser > Scheduling > Scheduler > Set up > Generate resource availability
4. Go into Production Supervisor(OPM) and create a new batch > view the batch > (Menu) Tools > Workday Calendar
it's expected the new calendar to be used, but it still shows the old calendar.
Solution