R12 OPM New Calendar not Showing as Workday Calendar in Production Batch (Doc ID 1961910.1)

Last updated on JUNE 30, 2016

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Which calendar will be considered in OPM production batch? resource calendar or inventory organization calendar?

1. Setting up the calendar in Inventory:
Inventory > Set up > Organizations > Calendars > Create calendar in Workday calendar > Tools > Build

2. Attach calendar to resource in process engineer:
Process engineer > Set up > Plant resources > Resource information > Search resource information > Add required calendar into calendar field in both material and labour plant resources

3. To generate resource availability in OPM Supply chain superuser:

OPM Supply chain superuser > Scheduling > Scheduler > Set up > Generate resource availability

4. Go into Production Supervisor(OPM) and create a new batch > view the batch > (Menu) Tools > Workday Calendar
it's expected the new calendar to be used, but it still shows the old calendar.


 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms