My Oracle Support Banner

R12 OPM New Calendar not Showing as Workday Calendar in Production Batch (Doc ID 1961910.1)

Last updated on SEPTEMBER 01, 2023

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Which calendar will be considered in OPM production batch? resource calendar or inventory organization calendar?

1. Setting up the calendar in Inventory:
Inventory > Set up > Organizations > Calendars > Create calendar in Workday calendar > Tools > Build

2. Attach calendar to resource in process engineer:
Process engineer > Set up > Plant resources > Resource information > Search resource information > Add required calendar into calendar field in both material and labour plant resources

3. To generate resource availability in OPM Supply chain superuser:

OPM Supply chain superuser > Scheduling > Scheduler > Set up > Generate resource availability

4. Go into Production Supervisor(OPM) and create a new batch > view the batch > (Menu) Tools > Workday Calendar
it's expected the new calendar to be used, but it still shows the old calendar.


 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.