Not Able To Create Tasks With Same Start Date As Project, When Project created with API (Doc ID 1967146.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Foundation - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

1. A project has been created using the API with actual start date (22-JAN-2015 09:04:42)
2. A new task is manually added on the project but the default start date is without the time (22-JAN-2015 00:00:00)

How to avoid the following errors:
          'APP-PA-19091:Start date must be earlier than all tasks start dates.
          Cause: A project cannot have a start date that is later than the start date of any of its tasks.' (PA_PR_INVALID_START_DATE)
or
          'APP-OKE-248023: The contract effective dates exceed the project effective dates.' (OKE_DATE_EXCEED_PROJ_DATE)

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms