Goal

After applying Procurement RUP July 2014: <Patch 18911810>, when requisition lines are added to an existing Purchase Order (PO) that is tied to Contract Purchase Agreement (CPA), the PO Header Level Default Ship-To Location is changed to that of the new line. The line level Deliver-To Location does remain the same. This issue is occurring in both Buyer Work Center (BWC) as well as in the core Purchasing form.