Preventive Maintenance (PM) Schedule Dates Incorrectly Calculated When There Are Multiple Activities (Doc ID 1984026.1)

Last updated on OCTOBER 04, 2016

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Enterprise Asset Management PM Schedule dates are incorrectly calculated when a schedule has more than one activity.  Only one of the activities correctly has correctly calculated schedule dates.  The other activities have incorrectly calculated schedules.


EXPECTED BEHAVIOR

All activities in the PM Schedule should have correctly calculated schedule dates.


STEPS

The issue can be reproduced as shown in the example below:
1. EAM: Schedule: Schedule Definition: Query schedule Schedule-X, asset = Asset-1, Actual End Date = 15-OCT-2014
2. The schedule has two asset activities, Activity-1 and Activity-2
3. EAM: Work Order Planning: Maintenance Workbench: Forecast Schedule using Maintenance Work Bench


    Activity-1 has dates schedule 11-14-2014, 12-14-2014, 1-13-2015.............. Last Service Date = 15-OCT-2015  

    Activity-2 has date 1-13-2015....... Last Service Date = 20-Aug-2014.  Based on the Service Interval and last service date, Activity-2 should have had WO setup for 20-Nov-2014




Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms