Symptoms

If the resource assignment is created by the PA_TASK_ASSIGNMENTS_PUB.CREATE_TASK_ASSIGNMENTS API, then it does not appear on the LOV for the resource
in the task details. If it is created in the front end, then it is in the LOV and can be assigned to the task.

Cause