adop prepare cutover Phase is Hanging ; Running Forever in multi-node (Doc ID 1986770.1)

Last updated on OCTOBER 30, 2024

Applies to:

Oracle Applications DBA - Version 12.2 and later
Information in this document applies to any platform.

Symptoms

 On EBS R12.2 multinode instance, if the number of nodes exceed 10, then adop cutover is hanging forever.  The prepare phase has started running on the some of the secondary nodes, but not starting on the Primary node (where Admin server is running).

 $ adop phase=prepare

Node Name Node Type Phase Status Started   
--------------- --------------- --------------- --------------- 
<HOST_01> <strong>master</strong> PREPARE <strong>NOT STARTED</strong> 
 
 
<HOST_02> slave PREPARE RUNNING 24-FEB-15 02:30:44 +00:00 
<HOST_03> slave PREPARE RUNNING 24-FEB-15 07:59:42 +00:00 &lt;&lt;&lt;&lt;&lt; Started 5.5 hours later than others.
<HOST_04> slave PREPARE RUNNING 24-FEB-15 02:30:44 +00:00 
<HOST_05> slave PREPARE RUNNING 24-FEB-15 02:32:30 +00:00 
<HOST_06> slave PREPARE <strong>NOT STARTED</strong>

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.