My Oracle Support Banner

R12 View Workplan Cost (Task Summary) - Wrong Calculations for Remaining Cost (Doc ID 1988394.1)

Last updated on FEBRUARY 15, 2019

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

 In the View Workplan Cost (Task Summary) - the "Remaining Cost" and "Remaining Effort" calculations are incorrect.

It brings back values as shown below:

Total Effort: 50
Actual Effort: 8
Remaining Effort: 50 (Expected value = 42)
-----------------------------------------------------------------------------------
Total Cost: 1,440,000
Actual Cost: 1,383,000
Remaining Cost: 1,440,000 (Expected value = 57,000)

Why are the expected values not displayed?

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.