20181483 Payment Is Processed Twice In PA; At Entry And Reconciliation (Doc ID 1990693.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

On 12.1.1 and later In cash basis ledger a payment is interfaced into PA when entered. Actual costs increases by the paid amount and the commitment amount decreases by the payment amount.
When later on the payment is reconciled in cash management again the actual costs are increased by the payment amount and the commitment amount is decreased by the payment amount.
This is causing the costs to double and the commitment to decrease the double amount.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.