Propagate ECO Not Updating Child Organization ECO STATUS To Scheduled (Doc ID 1995473.1)

Last updated on APRIL 02, 2015

Applies to:

Oracle Engineering - Version 12.2.2 and later
Information in this document applies to any platform.

Symptoms

On :  12.2.2 version, ECO

ACTUAL BEHAVIOR  
---------------
Find that Propagate ECO Not updating Child Org ECO STATUS  to Scheduled  at the time Propagate ECO for Deviations

EXPECTED BEHAVIOR
-----------------------
Expect the ECO when updated to Scheduled should update the Child org ECO to Scheduled but it is changing the status to 'Open'

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Change status of the Parent to Scheduled
2. Tools > Propagate ECO
3. Find that the Child status is changed to Open

Note that the Revised Items are all changed to Scheduled but the ECO status itself is being created as 'Open'

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms