ACTUAL BEHAVIOR
The Component Pick Release quantities picked are incorrect, as the rounded quantities for the job components are not considered

EXPECTED BEHAVIOR
The Component Pick Release quantities picked should be correct.

STEPS
The issue can be reproduced at will with the following example:

1)Create a BOM FG A -COMPONENT B(1) Yield 10%
2)Create a JOB for qty 11 with over completions tolerence set to 30%
3)Move qty 11 in option 10 and over complete 13
4)Move to que of operation 20 and scrap 2
5)Adjust component Quantities in Job & Schedules and reduce and round Component quantity
6)Run component pick ,picked quantities are not rounded


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms