Amortized Capacity Adjustments That Overlap Are Not Correctly Updating the Capacity Amount (Doc ID 1998303.1)

Last updated on OCTOBER 10, 2016

Applies to:

Oracle Assets - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

When trying to backdate an amortized production capacity adjustment that overlaps a previous transaction, the production capacity amount is incorrect when you go back into the asset.
This ONLY occurs in situations where a warning error appeared:  APP-OFA-48676: You are attempting to overlap this amortization with a previous transaction. Proceed with this amortization?

If you do not overlap and get this message, the production capacity saves correctly.