Symptoms

After upgrade to 12.2 from 11i,  there is a mismatch in the Top Task Name for the projects in the View Budget Summary page:

Steps to reproduce the issue:
======================
Project Management:
ES PA Management Super User (OU_ENVS_AFTL_GB)
Projects Delivery
Search Projects

-Click on Advanced Search:

-In the Project Number field give the value "100002100" and click on Go

-Click on the Project Name link and then click on the Financial Tab on top of the screen and get warning:

Warning:
To view financial plan summaries, please run the PRC: Delete Project Performance Reporting.

-Now click on the view against the plan type "As Sold Cost and Revenue Estimate":

-Then Click on Expand All in the Budget lines section:


-With the same navigation on release 11i while viewing the Budget summary:

Outline Nubmer Project or Task Name column:
-------------------------------------------
0                         XXXXXX
  1                        Engineering
  2                        Manufacturing


-In R12 while viewing the Budget Summary for the same project:


Outline Nubmer Project or Task Name column:
-------------------------------------------
0                        YYYYYY
  1                       Engineering
  2                       Manufacturing


==> There is a difference in the value for 'Project or Task Name' for the top task (Outline Number 0).



Changes

 Upgraded from R11i to 12.2

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms