Symptoms

On : 12.1.3 version, Workplan

When attempting to indent any task on any project, the following error occurs.

ERROR
-----------------------
Error
1. This action cannot be successfully completed due to the following errors.
2. XXXX: You cannot change the parent task for this task.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open the Project Workplan -> Tasks -> Update Tasks screen
2. Click on the Indent button
3. Error is encountered


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.