Symptoms

On : 12.1.3 version, Planner workbench

ACTUAL BEHAVIOR
---------------
The Oracle Inventory > Items > organization Items > Lead time tab processing lead time for a purchased item is being ignored in the results of an Enforce Demand Due Dates constrained plan

EXPECTED BEHAVIOR
-----------------------
Expect the processing lead time to result in a difference between the Suggested Start Date and Suggested Due Date

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Establish a purchased item with some processing lead time
2. Run the ASCP Standard Collection, complete refres
3. Run the Enforce Demand Due Dates constrained plan

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot understand why the processing lead time has not been applied

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.