ASCP with OPM the raw material purchase processing lead time from the item is not respected (Doc ID 2016851.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.10.2 and later
Oracle Process Manufacturing Process Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Planner workbench

ACTUAL BEHAVIOR
---------------
The Oracle Inventory > Items > organization Items > Lead time tab processing lead time for a purchased item is being ignored in the results of an Enforce Demand Due Dates constrained plan

EXPECTED BEHAVIOR
-----------------------
Expect the processing lead time to result in a difference between the Suggested Start Date and Suggested Due Date

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Establish a purchased item with some processing lead time
2. Run the ASCP Standard Collection, complete refres
3. Run the Enforce Demand Due Dates constrained plan

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot understand why the processing lead time has not been applied

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms